Carr Street pavement reconstruction

Carr Street from Chapman to Main Street — the subject of many resident complaints — is getting a full concrete rebuild thanks to a $505,287 contract with the low bidder. Expect construction detours and temporary parking changes from this summer through March 2027.

4 mentions (1 this month)Last discussed Oct 20, 2026
MediumRoads

FM 423 median lighting repairs

58 light fixtures along the 3.75-mile stretch of FM 423 are damaged or dark. A $382,000 contract will fix them all, with work done in four to six weeks.

2 mentions (1 this month)Last discussed Oct 7, 2026
HighRoads

Sidewalk repair backlog

A resident documented six broken sidewalks reported as far back as 2023 that still haven't been fixed — including one that sent his wife to the ER and another where he fell himself. He called the delays unacceptable for a city with residents who rely on walking.

2 mentionsLast discussed Aug 18, 2026
HighRoads

Turner Road Bridge repair

The bridge over the creek is a problem — and for some residents it's the only way in and out. Council added $43,540 for Olsson's design work, with construction expected around $500,000.

1 mentionLast discussed Aug 18, 2026
HighRoads

North Colony Blvd flooding fix

The stretch of North Colony between Squires and Page Road floods badly because four small inlets can't handle runoff draining from Page Road. The project adds three 20-foot inlets and upsizes pipes to 30-inch to store more water underground.

1 mentionLast discussed Jul 7, 2026