Summary
The stretch of North Colony between Squires and Page Road floods badly because four small inlets can't handle runoff draining from Page Road. The project adds three 20-foot inlets and upsizes pipes to 30-inch to store more water underground.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jul 7, 2026.
Impact analysis
Costs $453,619, funded through the approved 2025-26 capital improvement program.
Drivers and residents along the flooded corridor get a safer, drier roadway by November.
Commuters may face brief delays since only one lane will stay open in each direction during construction.